ETH Zurich's weekly web journal - auf deutsch
ETH Life - wissen was laeuft ETH Life - wissen was laeuft


ETH Life - wissen was laeuft ETH Life - wissen was laeuft
Home

ETH - Eidgenoessische Technische Hochschule Zuerich - Swiss Federal Institute of Technology Zurich
Section: Campus Life
deutsche Version english Version
Print-Version Drucken

Published: 01.09.2005, 06:00
Modified: 02.09.2005, 14:20
ETH project "House of Science" in Bamiyan (Afghanistan)
Building under difficult conditions

The "castle in the air" has gained a concrete floor and, soon, work on the walls will begin. Nevertheless, how work on the "ETH House of Science" in Bamiyan will continue to progress depends on when the winter arrives in central Afghanistan.

Peter Rüegg

Asef Alemyar directs his croaky voice into the telephone. The flu has the engineer in its grip – precisely in the week that he is visiting Switzerland with the purpose of informing about the construction progress in Bamiyan and talking to architects about the advancement of the project. Last Thursday Alemyar flew back to Afghanistan.

Reason for the urgency lies in the short summer in central Afghanistan. Very soon, perhaps already mid-September, winter will arrive in the high valleys; Bamiyan lies at an altitude of 2,500 metres. Roads and passes will be inaccessible and temperatures will sink to well below zero. Work on the construction site of the "House of Science", a meeting centre for the University of Bamiyan, will come to a standstill until spring. And spring arrives late in these parts. The beginning of April is the earliest date that can be envisaged for workers to take up their tools again. In the short time that remains Alemyar wants to get the walls of the ground floor and its ceiling finished. This autumn, the high-insulating windows are supposed to be transported from Switzerland to Bamiyan. There they will pass the winter - installed or not - depending on the weather.

Wet spring delayed construction

The weather has thwarted the building supervisor right from the start. The past winter was exceptionally long, so the first turning of the sod did not take place until the end of April, says Alemyar, who holds both Afghan and Swiss citizenship. By mid-June it had rained almost continuously for two months, which delayed work even more, and worse still, the rain had washed away a major supply route for the Bamiyan valley. Construction problems have also caused Alemyar plenty of trouble. On the spot where the foundation was to be placed, workers discovered underground storerooms at a depth of 2.8 metres, belonging to semi-nomadic people who lived in the area. These storerooms first had to be filled with concrete in order to secure the foundation. Alemyar: "As an expert I can't build on sandy ground". However, the foundation for the "House of Science" is now laid. A frost bar has been installed and pipes have been laid down.

The purchase of building material is also a difficult undertaking, because Alemyar cannot use the region's traditional clay bricks for the "House of Science". "Earthquakes are a common occurrence in the region. Therefore, the construction has to be earthquake-resistant, so we are using concrete," he says. This has its disadvantages. Components, such as cement or reinforcement bars, have to be brought from Pakistan or Iran, at best from Kabul, and this makes them as expensive as they are in Switzerland. The condition of the road linking Kabul and Bamiyan is so bad that it takes lorries two or three days to overcome the 230 kilometres between the two places. "We are anxious every time, whether an expected supply will arrive, because serious accidents are a daily occurrence on this route", explains Alemyar.


Afghanistan: between abyss and awakening

Afghanistan is a war-torn and war-shaken country. 26 years of war, first against Russian occupation, then against the Taliban regime, have brought this country in central Asia to the brink of ruin. There is a lack of everything wherever one looks. The education system has been razed to the ground. There is a shortfall of 29,000 in teachers. 85 per cent of the female population over 15 can neither read nor write. Security is precarious in many places. Drug barons and scattered groups of the Taliban threaten the very lives of the population. Also the economy is destroyed. Instead, the opium production and trade is flourishing. Production of the opium poppy rose between 2002 and 2004 from 3400 to 4200 tonnes. Today, Afghanistan covers 95 per cent of Europe's heroin demands and 87 per cent of the world's production of opium (1).




continuemehr

A motor-driven concrete vibrator is one of the few technical tools on the construction site in Bamiyan. (Picture: A. Alemyar) large

On the construction site itself, there is no crane, no dumper, no cement mixer. "All the machines that are standard equipment on a construction site in Switzerland don't exist in the Bamiyan valley," explains the engineer, who also supervises other constructions in Afghanistan. Nobody is very interested in building anything here. This means that there is no lack of builders. Over 80 are working on the ETH project, mixing concrete, transporting heavy loads, laying out the reinforcement bars. A tonne of concrete converts into 16 wheelbarrow loads, filled by hand, divided and distributed.

Architects are pleased

It took them some time to adapt to the situation in Bamiyan, say the three young architects Wolfgang Rossbauer, Ivica Brnic and Florian Graf. Nevertheless, in view of the difficulties, they were "more or less satisfied"–as is construction supervisor Alemyar–with the progress that had so far been made on the project. It was, however, difficult to have to accept not having full control over the building process. On the other hand, they were glad that they had someone to supervise the building who not only had the work carried out in their interests, but who also understood the national culture. "It's the best solution for everyone. We would probably never really be able to understand the cultural contrasts," they admit.

For the three ETH graduates, the "House of Science" has priority even though they are currently busy with completing their studies and working. "Flexibility" is their motto. They will probably be able to see their "castle in the air" in Bamiyan for themselves sometime next year. No concrete plans have been made yet though, except that their visit should coincide with Asef Alemyar's presence at the site.


A "castle in the air" becomes a place of encounter

The ETH project "House of Science“ in Bamiyan is the result of a competition (2) launched in 2004 by the Department of Architecture, Civil Engineering and Geomatic Sciences as part of this year's 150-year Jubilee at ETH Zurich. The winning project was "Polynational“, a creation from three students of architecture, Wolfgang Rossbauer, Ivica Brnic and Florian Graf. Originally, the project was conceived as a sort of architectonic theatre to be staged on the Poly terrace. Following their victory, the winners had another idea: to actually realise their project in Afghanistan in order to contribute to the restoration of the war-torn country. This is how the "castle in the air" mutated into the "House of Science“, a centre of encounter for students in Bamiyan. (3)




Footnotes:
(1) Further information on Afghanistan: Albert A. Stahel and Claudine Nick: Nation Building Afghanistan, Beilage zur ASMZ 7/8, Juli 2005. Order address: Redaktionssekretariat ASMZ, Huber & Co. AG, Postfach, 8501 Frauenfeld, Tel. 052 723 56 22, redaktion@asmz.ch
(2) Cf. ETH Life article: archiv.ethlife.ethz.ch/articles/luftschlabschlwett.html
(3) Cf. ETH Life article: archiv.ethlife.ethz.ch/articles/bamiyanpodium.html



You can write a feedback to this article or read the existing comments.




!!! Dieses Dokument stammt aus dem ETH Web-Archiv und wird nicht mehr gepflegt !!!
!!! This document is stored in the ETH Web archive and is no longer maintained !!!